Construction Progress – Park Lofts Airport
In this video, we present the current construction progress, recorded in April 2025 – featuring stunning drone footage.
Status as of August 13, 2025:
-
Concrete structure: 100%
-
Masonry: 89%
-
Exterior plaster: 80%
-
Interior plaster: 61%
-
Sanitary installations: 67%
-
Fire protection systems: 65%
-
Subfloor and floor coverings: 46%
-
Insulation: 50%
-
Electrical installations: 40%
-
Windows: 20% (installation of pre-frames)
-
Painting: 15% (beginning of putty application)
-
Roof: 60% (metal structure completed, installation of thermo-acoustic sheets underway)
Status as of September 18, 2025:
The development is in an advanced phase, with finishing work and specialized systems in progress:
-
Ground floor parking pavers: being installed
-
Fire doors: installed on Ground Floor and 1st Level
-
Stairwell pressurization system: in preparation
-
Apartment wiring, Level 1: in progress
-
Floors, baseboards, and grouting, Level 1: advancing
-
Aluminum openings: glass on Level 1, frames on Level 2
Exterior works include plastering of the rear façade and preparation of the rooftop level, while metal stair railings are being installed from Level 3 downwards.
Estimated Completion:
September 2025 – meaning just about 9 months total construction time for this modern, high-quality loft building in Asunción.