Construction Progress – Park Lofts Airport
Status as of August 2025:
-
Concrete structure: 100%
-
Masonry: 89%
-
Exterior plaster: 80%
-
Interior plaster: 61%
-
Sanitary installations: 67%
-
Fire protection systems: 65%
-
Subfloor and floor coverings: 46%
-
Insulation: 50%
-
Electrical installations: 40%
-
Windows: 20% (installation of pre-frames)
-
Painting: 15% (beginning of putty application)
-
Roof: 60% (metal structure completed, installation of thermo-acoustic sheets underway)
Status as of September 2025:
-
The development is in an advanced phase, focusing on finishing work and specialized systems:
-
Ground floor parking pavers: being installed
-
Fire doors: installed on Ground Floor and 1st Level
-
Stairwell pressurization system: in preparation
-
Apartment wiring Level 1: in progress
-
Floors, baseboards, and grouting Level 1: advancing
-
Aluminum openings: glass on Level 1, frames on Level 2
-
-
Exterior works include plastering of the rear façade and preparation of the rooftop level
-
Metal stair railings are being installed from Level 3 downwards
Status as of October 2025:
Park Lofts Airport continues to make remarkable progress just 10 months after construction began in December 2024, nearing completion. The building is almost ready to welcome the first students from nearby universities like UMAX.
Recent Highlights:
-
Level 1:
-
100% completion of floors, tiling, wooden doors, and aluminum windows
-
Electrical distribution rails and internal wiring are 90% complete, with only final details remaining
-
-
Level 2:
-
Porcelain flooring 90% complete; bathroom floors 30% installed
-
Bathroom wall tiles at 25% progress; aluminum windows fully installed
-
Electrical distribution rails and internal wiring 90% finished
-
-
Water Infrastructure:
-
Installation of two upper tanks (10,000 liters each) and one lower tank (15,000 liters) fully completed
-
Final assembly of accessories underway
-
-
Ground Floor:
-
Paver flooring 100% finished, on schedule and fully functional
-
-
Façade/Exterior:
Exterior plasterwork progress at 35%, steadily advancing toward completion
Status as of November 2025:
The project has entered its final execution stage, with exterior works, safety systems, and access infrastructure nearing completion.
Recent Highlights:
Street Sidewalks (Asunción Street):
Sidewalk works are in the final stage of completion.
Roof:
Installation of laminated ventilation shafts fully completed.
Safety Systems:
Signage and emergency lighting fully installed and operational across the building.
Villalba Street Access:
Ramps and gates installed and fully operational.
España Street Façade:
Glazed façade surface in final finishing phase.
Asunción Street Access:
Ramp, gate, and perimeter fencing fully completed and in operation.
Status as of December 2025:
Park Lofts Airport has officially entered its final development phase, focusing on completion procedures, operational readiness, and coordination of unit handovers to investors.
Transition into final development and pre-delivery stage.
Investor Relations:
Communication initiated with investors to coordinate the handover process and confirm receipt of final project communications.
Operational Preparation:
Administrative and logistical coordination underway for apartment deliveries.
Next Steps:
Final inspections, documentation, and scheduling of unit handovers.