Construction Progress – Park Lofts Recoleta
Modern Living in the Heart of Recoleta
Park Lofts Recoleta Reaches a New Milestone – April 2025 Construction Update
Asunción, Paraguay | Footage: Late April 2025
Status as of August:
The development has reached 36% of the concrete structures completed, with the following progress:
-
Foundations: 90% completed
-
Ground Floor: 100% completed (including double-height ceiling)
-
First residential level: 100% completed
-
Second concrete slab poured on August 12
Although the percentages show significant progress, it is important to note that a large part of the concrete volume corresponds to the foundations and the double-height ground floor — both key structural elements in this project.
Status as of September:
The development achieved new milestones with the large-scale installation of structural elements:
-
21 columns installed
-
Staircase Ground Floor → 1st Level: formwork and reinforcement completed
-
Ground Floor: 100% of formwork removed
-
Perimeter Safety Platform: installed (except for service lift area)
-
Payment Certificate #4: verified and approved
-
PD slab: fully poured
-
Staircase Ground Floor → 1st Level: installed
-
Masonry, First Typical Floor: under construction
-
Columns, 4th Level: layout verified and approved
The layout of masonry on Level 1 marks the beginning of the next construction phase, while the reinforcement beams on top of the balance beam further strengthen the structure. Ongoing verification of reinforcements and levels confirms the project's construction quality.
Status as of October:
After only 10 months of construction, the project is making impressive progress in one of the best neighborhoods of Asunción, in close proximity to all essential services and amenities.
Recent Highlights:
-
Fifth Floor Slab:
-
Successfully poured, representing a significant milestone in the construction schedule
-
Concrete pouring of two staircase sections completed, securing the building's vertical circulation
-
-
Level 1 and Level 2:
-
Masonry work completed, clearly defining spaces and further solidifying the building envelope
-
-
Level 1 Installations:
-
Electrical installation work has begun
-
Transformer pit and underground tank concreted
-
-
Level 1 Flooring:
-
Subfloor concrete completed
-
Application of screed has begun, preparing the surface for the next construction phase
-
Planned completion: June 2026
With a total construction time of around 15 months, this project will deliver a modern, high-quality apartment building.