Progreso Park Lofts Airport

En este video mostramos el avance actual de la obra, grabado en abril de 2025 – con impactantes tomas aéreas desde un dron.

Status as of August 13, 2025:

  • Concrete structure: 100%

  • Masonry: 89%

  • Exterior plaster: 80%

  • Interior plaster: 61%

  • Sanitary installations: 67%

  • Fire protection systems: 65%

  • Subfloor and floor coverings: 46%

  • Insulation: 50%

  • Electrical installations: 40%

  • Windows: 20% (installation of pre-frames)

  • Painting: 15% (beginning of putty application)

  • Roof: 60% (metal structure completed, installation of thermo-acoustic sheets underway)

Status as of September 18, 2025:

The development is in an advanced phase, with finishing work and specialized systems in progress:

  • Ground floor parking pavers: being installed

  • Fire doors: installed on Ground Floor and 1st Level

  • Stairwell pressurization system: in preparation

  • Apartment wiring, Level 1: in progress

  • Floors, baseboards, and grouting, Level 1: advancing

  • Aluminum openings: glass on Level 1, frames on Level 2

Exterior works include plastering of the rear façade and preparation of the rooftop level, while metal stair railings are being installed from Level 3 downwards.

Estimated Completion:
September 2025 – which means just 9 months of total construction time for this modern, high-quality loft building in Asunción.