Tower Pushes Forward with Its Deep Foundation Work

Construction Progress

Park Lofts Tower is pushing forward with its deep foundation work: numerous additional piles already completed, and the project remains firmly on schedule.

Park Lofts Tower under construction
Park Lofts Tower under construction.

Deep foundation work continues to progress on schedule. During the period, numerous additional foundation piles were successfully completed, and the team has already prepared new drilling positions, allowing the work to continue without interruption.

The building’s foundation is being built with deep foundation piles reaching depths of up to 23 meters, designed to guarantee the bearing capacity and structural stability of the future tower.

23 mDepth of the foundation piles
Deep foundationCurrent stage of construction
Next milestoneStart of the concrete superstructure
Foundation progress plan for Park Lofts Tower
Updated foundation plan: in green, the piles already completed; in red, those scheduled for the current week.

The updated plan clearly shows that a significant portion of the planned piles has already been completed, and that the project is moving forward continuously and on schedule.

In the coming weeks, work will continue on new deep foundation piles, ongoing foundation work, preparation for the next drilling and foundation stages, and progress on consolidating the building’s load-bearing foundation structure. With every pile completed, the base on which the tower will be built grows stronger, a key milestone ahead of the start of the reinforced concrete superstructure. The Park Lofts team is grateful for the trust placed in the project and will continue to support its progress through to delivery.